Dept. of Trans. PROGRESS Serial No. Contract No. 07-166-08-53 04-275104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 51% 61% 04-SOL-80-17.2/ .0 Federal Project: NONE Progress payment No. 05 Payment period ending: 06-20-07 GHILOTTI BROS INC 525 JACOBY STREET SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 659,617.50 204,773.15 2.a. Extra Work 12,528.93 10,050.52 b. Adjustment Comp. 3. Materials on Hand 26,400.51 0.00 4. Earned Subject to Retention 698,546.94 214,823.67 5. Mobilization 109,867.50 0.00 6. Total Work Completed 782,013.93 7. Deductions 8. a.Contract Retentions -34,927.35 -6,680.18 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 773,487.09 208,143.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 208,143.49