Dept. of Trans. PROGRESS Serial No. Contract No. 05-050-08-02 04-276004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 10% 5% 04-SON-101-3.5/3.9 Federal Project: ACNH-Q101(58) Progress payment No. 05 Payment period ending: 02-20-05 DIABLO CONTRACTORS INC 7 CROW CANYON COURT STE 100 SAN RAMON CA 94583 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 456,834.91 190,143.98 2.a. Extra Work 8,440.53 0.00 b. Adjustment Comp. 3. Materials on Hand 278,579.57 218,381.72 4. Earned Subject to Retention 743,855.01 408,525.70 5. Mobilization 440,000.00 440,000.00 6. Total Work Completed 905,275.44 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,183,855.01 848,525.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 848,525.70