Dept. of Trans. PROGRESS Serial No. Contract No. 23-230-13-32 04-281204 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 29% Location: Federal Project: 04-NAP-29-5.0/6.7 ACNH-X055(60) 04-NAP-221-0.0/0.7 Progress payment No. 013 Payment period ending: 08-20-23 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,746,924.87 1,177,870.32 2. a. Extra Work 920,354.21 41,426.11 b. Adustment Comp. 38,656.99 -191.35 3. Materials on Hand 152,487.00 -8,462.00 4. Earned Subject to Retention 14,858,423.07 1,210,643.08 5. Mobilization 2,850,000.00 0.00 6. Total Work Completed 17,555,936.07 7. Deductions -6,586.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,701,837.07 1,210,643.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,210,643.08