Dept. of Trans. PROGRESS Serial No. Contract No. 25-017-14-04 04-281204 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 65% Location: Federal Project: 04-NAP-29-5.0/6.7 ACNH-X055(60) 04-NAP-221-0.0/0.7 Progress payment No. 030 Payment period ending: 01-20-25 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,141,120.84 793,321.39 2. a. Extra Work 2,795,004.08 0.00 b. Adustment Comp. 794,326.29 0.00 3. Materials on Hand 4. Earned Subject to Retention 31,730,451.21 793,321.39 5. Mobilization 3,000,000.00 0.00 6. Total Work Completed 34,730,451.21 7. Deductions -92,586.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 34,637,865.21 793,321.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 793,321.39