Dept. of Trans. PROGRESS Serial No. Contract No. 11-111-14-41 04-283814 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 33% 04-SON-116-41.8/44.7 Federal Project: ACHS-P116(42) STP-P116(42) Progress payment No. 15 Payment period ending: 04-20-11 ARGONAUT CONSTRUCTORS P O BOX 639 SANTA ROSA CA 95402 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,598,523.69 92,177.85 2.a. Extra Work 762,812.00 70,837.12 b. Adjustment Comp. 114,226.00 0.00 3. Materials on Hand 128,431.02 5,361.11 4. Earned Subject to Retention 8,603,992.71 168,376.08 5. Mobilization 440,000.00 0.00 6. Total Work Completed 8,915,561.69 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,043,992.71 168,376.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 168,376.08