Dept. of Trans. PROGRESS Serial No. Contract No. 13-239-12-21 04-283824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 30% 04-SON-116-41.8/44.7 Federal Project: ACHS-P116(44) STP Progress payment No. 05 Payment period ending: 08-20-13 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 523,769.00 253,251.75 2.a. Extra Work 24,482.70 10,476.72 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 548,251.70 263,728.47 5. Mobilization 180,500.00 38,000.00 6. Total Work Completed 728,751.70 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 728,751.70 301,728.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 301,728.47