Dept. of Trans. PROGRESS Serial No. Contract No. 14-142-11-01 04-283824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 04-SON-116-41.8/44.7 Federal Project: ACHS-P116(44) STP Progress payment No. 13 Payment period ending: 05-20-14 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,340,939.20 5,713.00 2.a. Extra Work 90,491.58 28,771.87 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,431,430.78 34,484.87 5. Mobilization 190,000.00 0.00 6. Total Work Completed 1,621,430.78 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,621,430.78 34,484.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 34,484.87