Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 06-180-08-04 04-284314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 50% 04-ALA-580-18.8/R30.8 Federal Project: ACIM-580-1(45) Progress payment No. 08 Payment period ending: 06-20-06 R AND L BROSAMER R E SERRANO INC A JOINT VENTURE P O BOX 238 ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,048,557.28 425,000.00 2.a. Extra Work 9,503.90 0.00 b. Adjustment Comp. 3. Materials on Hand 89,555.67 0.00 4. Earned Subject to Retention 10,147,616.85 425,000.00 5. Mobilization 1,900,000.00 0.00 6. Total Work Completed 11,958,061.18 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,047,616.85 425,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 425,000.00