Dept. of Trans. SEMI-FINAL Serial No. Contract No. 07-100-14-24 04-284314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-ALA-580-18.8/R30.8 Federal Project: ACIM-580-1(45) Progress payment No. 16 Payment period ending: 12-20-06 R AND L BROSAMER R E SERRANO INC A JOINT VENTURE 1777 OAKLAND BLVD., STE 300 WALNUT CREEK, CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,176,182.21 21,454.95 2.a. Extra Work 448,175.54 77,621.95 b. Adjustment Comp. 142,831.10 60,218.40 3. Materials on Hand 4. Earned Subject to Retention 20,767,188.85 159,295.30 5. Mobilization 2,000,000.00 0.00 6. Total Work Completed 22,767,188.85 7. Deductions 0.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 22,767,188.85 169,295.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 169,295.30