Dept. of Trans. PROGRESS Serial No. Contract No. 04-022-18-13 04-284904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 75% 60% 04-SCL-101-45.5/45.9 Federal Project: NONE Progress payment No. 20 Payment period ending: 01-20-04 AMLAND 3168 KNIGHTS BRIDGE RD SAN JOSE CA 95132 Escrow No. 01758 Total Estimate This Estimate 1. Contract Itms Without Mobil. 378,261.50 3,500.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 378,261.50 3,500.00 5. Mobilization 50,000.00 0.00 6. Total Work Completed 428,261.50 7. Deductions 8. a.Contract Retentions -18,913.08 -175.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 409,348.42 3,325.00 10. Reduction Amt to Escrow 11. Payment to Escrow 18,730.00 12. Net Pymt. this Estimate 3,325.00