Dept. of Trans. PROGRESS Serial No. Contract No. 02-205-08-12 04-285524 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 49% 34% 04-SCL-880-9.9/10.5 Federal Project: 04-ALA-880-R0.0/R0.4 ACNH-880-1(47) I-880-1(47) Progress payment No. 12 Payment period ending: 07-20-02 BAY CITIES PAVING AND GRADING INC P O BOX 6227 CONCORD CA 94524 Escrow No. 01804 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,216,217.86 1,070,014.70 2.a. Extra Work 481,967.14 221,175.00 b. Adjustment Comp. 911,586.42 151,610.00 3. Materials on Hand 431,823.31 -107,473.54 4. Earned Subject to Retention 13,041,594.73 1,335,326.16 5. Mobilization 1,947,500.00 0.00 6. Total Work Completed 14,557,271.42 7. Deductions -20,000.00 -10,000.00 8. a.Contract Retentions -652,079.74 -66,766.31 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,317,014.99 1,258,559.85 10. Reduction Amt to Escrow 11. Payment to Escrow 652,070.00 12. Net Pymt. this Estimate 1,258,559.85