Dept. of Trans. PROGRESS Serial No. Contract No. 08-358-10-22 04-290844 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 3% 04-ALA-580-R7.8/13.2 Federal Project: HPLU-6204(70) L-6204(70) Progress payment No. 05 Payment period ending: 12-20-08 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,218,777.42 1,447,821.40 2.a. Extra Work 101,986.68 25,221.47 b. Adjustment Comp. 3. Materials on Hand 205,343.90 205,343.90 4. Earned Subject to Retention 12,526,108.00 1,678,386.77 5. Mobilization 4,037,500.00 0.00 6. Total Work Completed 16,358,264.10 7. Deductions -30,000.00 -30,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,533,608.00 1,648,386.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,648,386.77