Dept. of Trans. PROGRESS Serial No. Contract No. 09-111-08-21 04-290844 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 45% 25% 04-ALA-580-R7.8/13.2 Federal Project: HPLU-6204(70) L-6204(70) Progress payment No. 09 Payment period ending: 04-20-09 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,862,049.05 1,766,648.65 2.a. Extra Work 301,781.35 67,396.89 b. Adjustment Comp. -317,407.55 -317,407.55 3. Materials on Hand 205,343.90 -10.00 4. Earned Subject to Retention 16,051,766.75 1,516,627.99 5. Mobilization 4,037,500.00 0.00 6. Total Work Completed 19,883,922.85 7. Deductions -19,560.00 5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 20,069,706.75 1,521,627.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,521,627.99