Dept. of Trans. PROGRESS Serial No. Contract No. 09-164-10-41 04-290844 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 44% 04-ALA-580-R7.8/13.2 Federal Project: HPLU-6204(70) L-6204(70) Progress payment No. 11 Payment period ending: 06-20-09 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,208,130.45 2,961,119.35 2.a. Extra Work 587,425.63 11,569.31 b. Adjustment Comp. -484,988.43 57,642.15 3. Materials on Hand 4. Earned Subject to Retention 23,310,567.65 3,030,330.81 5. Mobilization 4,250,000.00 212,500.00 6. Total Work Completed 27,560,567.65 7. Deductions -19,560.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 27,541,007.65 3,242,830.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,242,830.81