Dept. of Trans. PROGRESS Serial No. Contract No. 09-264-09-13 04-290844 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 77% 04-ALA-580-R7.8/13.2 Federal Project: HPLU-6204(70) L-6204(70) Progress payment No. 14 Payment period ending: 09-20-09 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,120,894.92 1,575,691.65 2.a. Extra Work 771,552.01 135,573.04 b. Adjustment Comp. -620,489.38 0.00 3. Materials on Hand 4. Earned Subject to Retention 31,271,957.55 1,711,264.69 5. Mobilization 4,250,000.00 0.00 6. Total Work Completed 35,521,957.55 7. Deductions -47,900.00 -35,840.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 35,474,057.55 1,675,424.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,675,424.69