Dept. of Trans. PROGRESS Serial No. Contract No. 09-294-09-41 04-290844 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 85% 04-ALA-580-R7.8/13.2 Federal Project: HPLU-6204(70) L-6204(70) Progress payment No. 15 Payment period ending: 10-20-09 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 32,179,355.47 1,058,460.55 2.a. Extra Work 828,124.08 56,572.07 b. Adjustment Comp. -620,489.38 0.00 3. Materials on Hand 4. Earned Subject to Retention 32,386,990.17 1,115,032.62 5. Mobilization 4,250,000.00 0.00 6. Total Work Completed 36,636,990.17 7. Deductions -52,900.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 36,584,090.17 1,110,032.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,110,032.62