Dept. of Trans. PROGRESS Serial No. Contract No. 09-328-09-33 04-290844 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 96% 04-ALA-580-R7.8/13.2 Federal Project: HPLU-6204(70) L-6204(70) Progress payment No. 16 Payment period ending: 11-20-09 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 32,671,191.35 491,835.88 2.a. Extra Work 1,197,542.43 369,418.35 b. Adjustment Comp. -925,571.53 -305,082.15 3. Materials on Hand 38,060.56 38,060.56 4. Earned Subject to Retention 32,981,222.81 594,232.64 5. Mobilization 4,250,000.00 0.00 6. Total Work Completed 37,193,162.25 7. Deductions -47,900.00 5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 37,183,322.81 599,232.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 599,232.64