Dept. of Trans. PROGRESS Serial No. Contract No. 09-356-09-01 04-290844 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 96% 04-ALA-580-R7.8/13.2 Federal Project: HPLU-6204(70) L-6204(70) Progress payment No. 17 Payment period ending: 12-20-09 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 32,689,850.29 18,658.94 2.a. Extra Work 2,090,524.93 892,982.50 b. Adjustment Comp. -902,631.53 22,940.00 3. Materials on Hand 38,060.56 0.00 4. Earned Subject to Retention 33,915,804.25 934,581.44 5. Mobilization 4,250,000.00 0.00 6. Total Work Completed 38,127,743.69 7. Deductions -47,900.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 38,117,904.25 934,581.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 934,581.44