Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 10-042-09-55 04-290844 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-ALA-580-R7.8/13.2 Federal Project: HPLU-6204(70) L-6204(70) Progress payment No. 19 Payment period ending: 02-02-10 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 33,501,286.20 651,884.80 2.a. Extra Work 2,929,261.40 404,160.60 b. Adjustment Comp. -801,711.95 66,990.07 3. Materials on Hand 0.00 -38,060.56 4. Earned Subject to Retention 35,628,835.65 1,084,974.91 5. Mobilization 4,250,000.00 0.00 6. Total Work Completed 39,878,835.65 7. Deductions -42,460.00 5,440.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 39,836,375.65 1,090,414.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,090,414.91