Dept. of Trans. PROGRESS Serial No. Contract No. 14-055-11-10 04-2908C4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 35% 04-ALA-580-R8.4/R14.6 Federal Project: ACIM-5801(105) Progress payment No. 13 Payment period ending: 02-20-14 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,300,698.77 5,557,578.38 2.a. Extra Work 374,501.60 95,363.49 b. Adjustment Comp. 204,407.03 19,891.55 3. Materials on Hand 265,096.14 -318,877.03 4. Earned Subject to Retention 19,144,703.54 5,353,956.39 5. Mobilization 4,275,000.00 0.00 6. Total Work Completed 23,154,607.40 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 23,409,703.54 5,353,956.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,353,956.39