Dept. of Trans. PROGRESS Serial No. Contract No. 14-112-11-05 04-2908C4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 45% 38% 04-ALA-580-R8.4/R14.6 Federal Project: ACIM-5801(105) Progress payment No. 15 Payment period ending: 04-20-14 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,928,937.27 -53,481.00 2.a. Extra Work 1,374,087.57 339,874.29 b. Adjustment Comp. 391,425.66 116,910.00 3. Materials on Hand 26,901.00 -127,051.00 4. Earned Subject to Retention 20,721,351.50 276,252.29 5. Mobilization 4,275,000.00 0.00 6. Total Work Completed 24,969,450.50 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 24,986,351.50 276,252.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 276,252.29