Dept. of Trans. PROGRESS Serial No. Contract No. 15-281-13-18 04-2908C4 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 78% Location: Federal Project: 04-ALA-580-R8.4/R14.6 ACIM-5801(105) Progress payment No. 032 Payment period ending: 09-20-15 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 43,889,387.81 2,922,677.59 2. a. Extra Work 14,439,170.45 82,949.65 b. Adustment Comp. 1,567,405.02 523,595.63 3. Materials on Hand 48,864.70 0.00 4. Earned Subject to Retention 59,944,827.98 3,529,222.87 5. Mobilization 4,500,000.00 0.00 6. Total Work Completed 64,395,963.28 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 64,434,827.98 3,529,222.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,529,222.87