Dept. of Trans. PROGRESS Serial No. Contract No. 15-293-18-29 04-2908C4 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 81% Location: Federal Project: 04-ALA-580-R8.4/R14.6 ACIM-5801(105) Progress payment No. 033 Payment period ending: 10-20-15 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 47,624,244.06 3,734,856.25 2. a. Extra Work 14,645,892.05 206,721.60 b. Adustment Comp. 819,718.82 -747,686.20 3. Materials on Hand 30,310.00 -18,554.70 4. Earned Subject to Retention 63,120,164.93 3,175,336.95 5. Mobilization 4,500,000.00 0.00 6. Total Work Completed 67,589,854.93 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 67,610,164.93 3,175,336.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,175,336.95