Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 14-062-09-07 04-2908E4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 48% 04-ALA-580-R14.6/R21.6 Federal Project: ACIM-5801(54) Progress payment No. 13 Payment period ending: 02-20-14 DESILVA GATES CONSTRUCTION LP P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,894,203.73 0.00 2.a. Extra Work 471,975.99 0.00 b. Adjustment Comp. 667,862.68 0.00 3. Materials on Hand 111,207.00 111,207.00 4. Earned Subject to Retention 13,145,249.40 111,207.00 5. Mobilization 3,657,500.00 0.00 6. Total Work Completed 16,691,542.40 7. Deductions -19,260.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,783,489.40 111,207.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 111,207.00