Dept. of Trans. PROGRESS Serial No. Contract No. 15-203-06-10 04-2908E4 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 88% Location: Federal Project: 04-ALA-580-R14.6/R21.6 ACIM-5801(54) Progress payment No. 032 Payment period ending: 07-20-15 DESILVA GATES CONSTRUCTION LP P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,538,843.11 906,497.30 2. a. Extra Work 8,383,099.23 84,130.98 b. Adustment Comp. 2,729,354.56 -211,535.50 3. Materials on Hand 117,994.30 -29,386.47 4. Earned Subject to Retention 42,769,291.20 749,706.31 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 46,501,296.90 7. Deductions -16,035.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 46,603,256.20 749,706.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 749,706.31