Dept. of Trans. SEMI-FINAL Serial No. Contract No. 16-271-09-58 04-2908E4 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-ALA-580-R14.6/R21.6 ACIM-5801(54) Progress payment No. 043 Payment period ending: 12-21-15 DESILVA GATES CONSTRUCTION LP PO BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 32,090,641.52 -255,660.80 2. a. Extra Work 10,889,575.02 118,749.57 b. Adustment Comp. 3,044,332.19 26,112.90 3. Materials on Hand 4. Earned Subject to Retention 46,024,548.73 -110,798.33 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 49,874,548.73 7. Deductions -16,035.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 49,858,513.73 -110,798.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -110,798.33