Dept. of Trans. PROGRESS Serial No. Contract No. 14-111-09-54 04-2908V4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 52% 53% 04-ALA-580-R7.8/R19.1 Federal Project: NONE Progress payment No. 14 Payment period ending: 04-20-14 O C JONES AND SONS INC 1520 FOURTH STREET BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,936,756.39 354,371.11 2.a. Extra Work 623,978.29 207,408.68 b. Adjustment Comp. 174,776.00 0.00 3. Materials on Hand 14,061.00 0.00 4. Earned Subject to Retention 12,749,571.68 561,779.79 5. Mobilization 2,356,000.00 0.00 6. Total Work Completed 15,091,510.68 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,105,571.68 561,779.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 561,779.79