Dept. of Trans. PROGRESS Serial No. Contract No. 04-233-11-22 04-291004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 54% 04-SF-101-4.7/5.1 Federal Project: ACNH-Q101(49) Progress payment No. 10 Payment period ending: 08-20-04 PROVEN MANAGEMENT INC 501 CESAR CHAVEZ BLVD STE 204 SAN FRANCISCO CA 94124 Escrow No. 02143 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,148,723.59 1,715,714.64 2.a. Extra Work 237,629.20 40,558.50 b. Adjustment Comp. 3. Materials on Hand 1,875,299.97 -361,389.17 4. Earned Subject to Retention 9,261,652.76 1,394,883.97 5. Mobilization 2,232,500.00 0.00 6. Total Work Completed 9,618,852.79 7. Deductions 8. a.Contract Retentions -469,652.59 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,024,500.17 1,394,883.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,394,883.97