Dept. of Trans. PROGRESS Serial No. Contract No. 05-140-18-17 04-291004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 87% 04-SF-101-4.7/5.1 Federal Project: ACNH-Q101(49) Progress payment No. 20 Payment period ending: 05-20-05 PROVEN MANAGEMENT INC 706 SANSOME STREET SAN FRANCISCO CA 94111 Escrow No. 02143 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,106,774.95 1,807,459.21 2.a. Extra Work 659,187.15 66,711.89 b. Adjustment Comp. 747,384.68 16,965.59 3. Materials on Hand 20,820.35 6,640.00 4. Earned Subject to Retention 21,534,167.13 1,897,776.69 5. Mobilization 2,350,000.00 0.00 6. Total Work Completed 23,863,346.78 7. Deductions 8. a.Contract Retentions -1,076,708.36 -94,888.84 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 22,807,458.77 1,802,887.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,802,887.85