Dept. of Trans. PROGRESS Serial No. Contract No. 05-325-14-18 04-291004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 04-SF-101-4.7/5.1 Federal Project: ACNH-Q101(49) Progress payment No. 26 Payment period ending: 11-20-05 PROVEN MANAGEMENT INC 706 SANSOME STREET SAN FRANCISCO CA 94111 Escrow No. 02143 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,795,227.60 950.00 2.a. Extra Work 967,527.82 187,566.15 b. Adjustment Comp. 969,371.09 0.00 3. Materials on Hand 4. Earned Subject to Retention 24,732,126.51 188,516.15 5. Mobilization 2,350,000.00 0.00 6. Total Work Completed 27,082,126.51 7. Deductions -114,840.00 0.00 8. a.Contract Retentions -1,236,606.33 -9,425.81 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 25,730,680.18 179,090.34 10. Reduction Amt to Escrow 11. Payment to Escrow 1,227,180.00 12. Net Pymt. this Estimate 179,090.34