Dept. of Trans. SEMI-FINAL Serial No. Contract No. 07-086-14-58 04-291004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SF-101-4.7/5.1 Federal Project: ACNH-Q101(49) Progress payment No. 35 Payment period ending: 10-06-06 PROVEN MANAGEMENT INC 706 SANSOME STREET SAN FRANCISCO CA 94111 Escrow No. 02143 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,046,770.20 0.00 2.a. Extra Work 1,364,616.60 26,874.92 b. Adjustment Comp. 1,068,951.62 118,368.07 3. Materials on Hand 4. Earned Subject to Retention 25,480,338.42 145,242.99 5. Mobilization 2,350,000.00 0.00 6. Total Work Completed 27,830,338.42 7. Deductions -114,840.00 500.00 8. a.Contract Retentions -1,265,692.27 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 1,265,692.27 0.00 9. Total pay to Contractor 27,715,498.42 145,742.99 10. Reduction Amt to Escrow -1,227,180.00 0.00 11. Payment to Escrow 1,227,180.00 12. Net Pymt. this Estimate 145,742.99