Dept. of Trans. PROGRESS Serial No. Contract No. 12-167-16-11 04-292274 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 9% 04-ALA-80-1.7/2.5 Federal Project: ER15-A200(4E) Progress payment No. 03 Payment period ending: 06-20-12 BAY CITIES PAVING AND GRADING INC P O BOX 6227 CONCORD CA 94524 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 295,123.78 34,015.00 2.a. Extra Work 7,738.51 7,738.51 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 302,862.29 41,753.51 5. Mobilization 41,800.00 8,800.00 6. Total Work Completed 344,662.29 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 344,662.29 50,553.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 50,553.51