Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 01-302-11-42 04-2922U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-ALA-880-32.6/33.2 Federal Project: ER-1546(3) Progress payment No. 29 Payment period ending: 10-05-01 PERFORMANCE EXCAVATORS INC 150 SHORELINE PARKWAY SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,312,380.41 -875.00 2.a. Extra Work 5,371,890.10 799.99 b. Adjustment Comp. 9,804.62 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,694,075.13 -75.01 5. Mobilization 232,000.00 0.00 6. Total Work Completed 7,926,075.13 7. Deductions -1,334.00 15,413.30 8. a.Contract Retentions -384,707.51 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 384,707.51 10,000.00 9. Total pay to Contractor 7,924,741.13 25,338.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 25,338.29