Dept. of Trans. PROGRESS Serial No. Contract No. 03-239-14-33 04-292364 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 28% 19% 04-ALA-880-32.7/34.0 Federal Project: ACIM-880-1(49) Progress payment No. 11 Payment period ending: 08-20-03 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 01965 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,896,830.70 154,698.00 2.a. Extra Work 64,001.85 583.46 b. Adjustment Comp. 4,100.00 0.00 3. Materials on Hand 190,209.22 128,519.31 4. Earned Subject to Retention 2,155,141.77 283,800.77 5. Mobilization 950,000.00 200,000.00 6. Total Work Completed 2,914,932.55 7. Deductions -1,600.00 0.00 8. a.Contract Retentions -197,983.69 -10,849.59 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,905,558.08 472,951.18 10. Reduction Amt to Escrow 11. Payment to Escrow 197,980.00 12. Net Pymt. this Estimate 472,951.18