Dept. of Trans. PROGRESS Serial No. Contract No. 05-019-10-17 04-2923A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 22% 04-ALA-880-34.8/35.0 Federal Project: 04-ALA-580-46.4/ .0 ER-1539(4) Progress payment No. 10 Payment period ending: 01-20-05 AMLAND 3168 KNIGHTS BRIDGE RD SAN JOSE CA 95132 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 281,739.70 11,975.70 2.a. Extra Work 22,685.13 0.00 b. Adjustment Comp. -4,061.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 300,363.83 11,975.70 5. Mobilization 32,000.00 0.00 6. Total Work Completed 332,363.83 7. Deductions 8. a.Contract Retentions -15,018.19 -598.78 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 317,345.64 11,376.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,376.92