Dept. of Trans. FINAL Serial No. Contract No. 16-139-15-20 04-294914 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-ALA-24-5.1/6.2 SARR-P024(30) 04-CC-24-0.0/1.3 A-P024(30) HPLU-6204(83) Progress payment No. 069 Payment period ending: 03-12-15 TUTOR-SALIBA CORP 15901 OLDEN ST SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 185,880,165.22 0.00 2. a. Extra Work 25,025,680.31 397,071.44 b. Adustment Comp. 55,818,381.87 786,697.12 3. Materials on Hand 4. Earned Subject to Retention 266,724,227.40 1,183,768.56 5. Mobilization 19,589,000.00 0.00 6. Total Work Completed 286,313,227.40 7. Deductions -890,128.50 1,681,540.50 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 285,423,098.90 2,865,309.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,865,309.06