Dept. of Trans. PROGRESS Serial No. Contract No. 10-167-09-31 04-294924 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 26% 26% 04-ALA-13-9.7/9.7 Federal Project: 04-ALA-24-5.4/5.4 ARRA-P024(31) L-P024(31) Progress payment No. 04 Payment period ending: 06-20-10 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 451,374.20 177,051.10 2.a. Extra Work 125.79 125.79 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 451,499.99 177,176.89 5. Mobilization 180,750.00 0.00 6. Total Work Completed 632,249.99 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 632,249.99 177,176.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 177,176.89