Dept. of Trans. PROGRESS Serial No. Contract No. 10-111-10-08 04-294934 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 24% 48% 04-ALA-24-5.4/5.4 Federal Project: ARRA-P024(32) L-P024(32) Progress payment No. 01 Payment period ending: 04-20-10 GHILOTTI BROS INC 525 JACOBY STREET SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 57,660.00 57,660.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 57,660.00 57,660.00 5. Mobilization 18,378.38 18,378.38 6. Total Work Completed 76,038.38 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 76,038.38 76,038.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 76,038.38