Dept. of Trans. PROGRESS Serial No. Contract No. 26-019-13-30 04-297634 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 79% Location: Federal Project: 04-ALA-84-17.9/22.9 NONE Progress payment No. 062 Payment period ending: 01-20-26 BAY CITIES PAVING& GRADING INC PO BOX 6227 CONCORD CA 945246227 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 115,546,001.55 209,671.70 2. a. Extra Work 12,213,538.82 212,205.23 b. Adustment Comp. 1,579,732.73 0.00 3. Materials on Hand 0.00 -24,765.33 4. Earned Subject to Retention 129,339,273.10 397,111.60 5. Mobilization 13,000,000.00 0.00 6. Total Work Completed 142,339,273.10 7. Deductions -10,200.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 142,329,073.10 397,111.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 397,111.60