Dept. of Trans. PROGRESS Serial No. Contract No. 26-294-13-17 04-297634 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 90% Location: Federal Project: 04-ALA-84-17.9/22.9 NONE Progress payment No. 071 Payment period ending: 10-20-26 BAY CITIES PAVING& GRADING INC PO BOX 6227 CONCORD CA 945246227 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 115,815,298.00 6,734.60 2. a. Extra Work 13,672,525.70 76,587.85 b. Adustment Comp. 1,547,432.73 0.00 3. Materials on Hand 0.00 -70,895.45 4. Earned Subject to Retention 131,035,256.43 12,427.00 5. Mobilization 13,000,000.00 0.00 6. Total Work Completed 144,035,256.43 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 144,035,256.43 12,427.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,427.00