Dept. of Trans. PROGRESS Serial No. Contract No. 14-169-08-32 04-2A1104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 11% 04-NAP-121-20.2/20.4 Federal Project: BHST-P121(25) Progress payment No. 03 Payment period ending: 06-20-14 GORDON N BALL INC 333 CAMILLE AVENUE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 279,914.00 231,818.00 2.a. Extra Work 8,211.98 7,042.26 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 288,125.98 238,860.26 5. Mobilization 142,500.00 142,500.00 6. Total Work Completed 430,625.98 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 430,625.98 381,360.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 381,360.26