Dept. of Trans. PROGRESS Serial No. Contract No. 14-233-08-16 04-2A1104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 47% 53% 04-NAP-121-20.2/20.4 Federal Project: BHST-P121(25) Progress payment No. 06 Payment period ending: 08-20-14 GORDON N BALL INC 333 CAMILLE AVENUE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 710,112.50 292,875.50 2.a. Extra Work 11,004.80 0.00 b. Adjustment Comp. 3. Materials on Hand 127,603.98 -43,804.50 4. Earned Subject to Retention 848,721.28 249,071.00 5. Mobilization 180,500.00 0.00 6. Total Work Completed 901,617.30 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,029,221.28 249,071.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 249,071.00