Dept. of Trans. PROGRESS Serial No. Contract No. 14-296-13-22 04-2A1104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 89% 04-NAP-121-20.2/20.4 Federal Project: BHST-P121(25) Progress payment No. 08 Payment period ending: 10-20-14 GORDON N BALL INC 333 CAMILLE AVENUE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,301,677.50 333,274.00 2.a. Extra Work 16,182.55 1,724.45 b. Adjustment Comp. 3. Materials on Hand 0.00 -76,777.50 4. Earned Subject to Retention 1,317,860.05 258,220.95 5. Mobilization 190,000.00 0.00 6. Total Work Completed 1,507,860.05 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,507,860.05 258,220.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 258,220.95