Dept. of Trans. PROGRESS Serial No. Contract No. 22-325-17-02 04-2A3324 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 38% Location: Federal Project: 04-ALA-84-13.6/18.0 HSNH-P084(55) Progress payment No. 019 Payment period ending: 11-20-22 BAY CITIES PAVING& GRADING INC PO BOX 6227 CONCORD CA 945246227 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,109,748.08 -421,416.10 2. a. Extra Work 813,837.05 0.00 b. Adustment Comp. 821,815.45 0.00 3. Materials on Hand 1,275,758.29 1,268,048.51 4. Earned Subject to Retention 17,021,158.87 846,632.41 5. Mobilization 1,578,235.10 0.00 6. Total Work Completed 17,323,635.68 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,599,393.97 846,632.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 846,632.41