Dept. of Trans. PROGRESS Serial No. Contract No. 15-111-08-57 04-2A4304 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 40% Location: Federal Project: 04-SCL-9-2.5/7.0 SSTP-S009(19) Progress payment No. 011 Payment period ending: 04-20-15 RGW CONSTRUCTION INC 550 GREENVILLE ROAD LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,178,368.72 -119,697.00 2. a. Extra Work 1,399,037.07 47,047.71 b. Adustment Comp. 938,428.96 239,964.80 3. Materials on Hand 4. Earned Subject to Retention 5,515,834.75 167,315.51 5. Mobilization 453,000.00 0.00 6. Total Work Completed 5,968,834.75 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,968,834.75 167,315.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 167,315.51