Dept. of Trans. PROGRESS Serial No. Contract No. 17-081-10-12 04-2A4904 PROGRESS PAYMENT VOUCHER %complete: %time: 11% 5% Location: Federal Project: 04-SF-280-R4.8/R6.2 ACIM-2801-1(246) Progress payment No. 001 Payment period ending: 03-20-17 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 400,357.70 400,357.70 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 53,020.00 53,020.00 4. Earned Subject to Retention 453,377.70 453,377.70 5. Mobilization 297,500.00 297,500.00 6. Total Work Completed 697,857.70 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 750,877.70 750,877.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 750,877.70