Dept. of Trans. SEMI-FINAL Serial No. Contract No. 18-152-10-49 04-2A4904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-SF-280-R4.8/R6.2 ACIM-2801-1(246) Progress payment No. 012 Payment period ending: 12-08-17 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,442,456.40 28,700.00 2. a. Extra Work 158,975.82 37,265.39 b. Adustment Comp. -28,700.00 -28,700.00 3. Materials on Hand 4. Earned Subject to Retention 5,572,732.22 37,265.39 5. Mobilization 595,000.00 0.00 6. Total Work Completed 6,167,732.22 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,157,732.22 37,265.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 37,265.39