Dept. of Trans. PROGRESS Serial No. Contract No. 10-298-13-47 04-2A5414 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 26% 36% 04-NAP-29-6.0/ .0 Federal Project: NONE Progress payment No. 02 Payment period ending: 10-20-10 FIELDSTONE CONSTRUCTION COMPANY 5915 FAUGHT ROAD SANTA ROSA CA 95403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 56,635.00 44,247.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 56,635.00 44,247.50 5. Mobilization 18,000.00 18,000.00 6. Total Work Completed 74,635.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 74,635.00 62,247.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 62,247.50