Dept. of Trans. PROGRESS Serial No. Contract No. 07-233-09-08 04-2A6704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 34% 04-ALA-238-3.5/ .0 Federal Project: 04-ALA-680-2.0/20.7 NONE Progress payment No. 02 Payment period ending: 08-20-07 BAY LINE CUTTING AND CORING INC 1033 YERBA BUENA AVE OAKLAND CA 94608 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 485,986.60 411,448.60 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 485,986.60 411,448.60 5. Mobilization 50,000.00 12,500.00 6. Total Work Completed 535,986.60 7. Deductions -200.00 0.00 8. a.Contract Retentions -24,299.33 -16,845.53 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 511,487.27 407,103.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 407,103.07