Dept. of Trans. FINAL Serial No. Contract No. 08-217-12-53 04-2A7004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-ALA-24-1.9/6.0 Federal Project: 04-ALA-980-0.0/1.9 NONE Progress payment No. 09 Payment period ending: 04-11-08 PENHALL COMPANY 13750 CATALINA STREET SAN LEANDRO CA 94577 Escrow No. 02321 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,761,363.90 1,375.00 2.a. Extra Work 17,046.64 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,778,410.54 1,375.00 5. Mobilization 77,000.00 0.00 6. Total Work Completed 1,855,410.54 7. Deductions 8. a.Contract Retentions -88,378.70 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 88,378.70 0.00 9. Total pay to Contractor 1,855,410.54 1,375.00 10. Reduction Amt to Escrow -88,370.00 0.00 11. Payment to Escrow 88,370.00 12. Net Pymt. this Estimate 1,375.00